Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt

RailCal app

site support

IRI - चाहे कितने भी हों मतभेद, फिर भी हम परिवार एक - Dr. Abhishek Rai

Search Forum
<<prev entry    next entry>>
Blog Entry# 5219997
Posted: Feb 16 2022 (21:41)

1 Responses
Last Response: Feb 17 2022 (18:40)
General Travel
12232 views
0

Feb 16 2022 (21:41)   MSH/Mahesana Junction (6 PFs)
riz339~
riz339~   5498 blog posts
Entry# 5219997            Tags  
Mehsana palanpur #doubling status
Status of Drgs:- 09 Nos. of ESP prepared and 7 Nos. ESP (PNU, MSH, UM SID, DRW, KMLI & UJA) approved from HQ. 02 Nos. under approval with CE/PL- CCG. Presently in process of approval of HQ. L-Section 13 Nos. approved from Div. and submitted to HQ. 10 Nos. L-Section approved by HQ and 03 Nos. under approval with HQ. ESPs will be approved with L-sections. SIP drawing will be submitted by Railway. All GADs and Drgs. other than ESPs and SIPs are to be prepared by EPC contractor and to be got approved from Railway. 04 Nos. ESP sent to CSTE(C) I/CCG for preparation of SIP on 17.12.21. Progress:- Alignment has been marked by the agency
...
more...
of FLS. In reference to Rly Bd. vide letter No. 2019/W-I/WR/SY/DL/PNU-MSH Dtd. 23.09.2019 the execution of MSH-PNU Doubling Project is to be implemented on EPC turnkey basis. EPC tender will be called for Civil,Track, S&T, Elect.(TRD) and Elect.(G) EPC tender document is under the approval of CSTE/C-1/WR EPC tender is under HQ Finance vetting. Compliance of observations has been submitted on 14.09.21 and re submitted after compliance and Railway Board has issued amendments in EPC document and same is under revision. EPC will be resubmitted to HQ Finance after incorporating all amendments. However, the amendments in EPC tender document and approval will consume more time, with reference to vision of Rly.BD the project is to be commissioned by 2024, hence GM – WR accorded sanction to execute the work by 2 packet systems (Rate contracts basis & EPC). MSH – Bhandu section and all yard work will be carried out on Rate contracts basis, and the remaining section can be done through EPC. NIT of MSH – BHU is under preparation. TDC :After finalization of EPC contract and other item rate contracts, the timeline shall be planned, however at present the indicative timeline is Dec-2023: Mahesana – Unjha 20.49 km)•Dec-2024: Unjha – Palanpur (42.121 km)

Translate to English
Translate to Hindi

8704 views
0

Feb 17 2022 (18:40)
amitarames
amitarames   265 blog posts
Re# 5219997-1              
Still no report of completion of Dangarwa Mehsana doubling nobody knows the status it was supposed to be completed by October '21 PNU MSH #Doubling will go to 2027 still under process
Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy