NI work is going on at Adra Yard for modification of signaling system as well as train operation.
After commissioning Adra EI will be 2nd largest EI in SER just after KGP.
After commissioning Adra EI will be 2nd largest EI in SER just after KGP.
Update of NI work Adra.
Day 1 - Dismantling of old X-over No.105A&105B with linking of X-over 132A&132B(Adra-Joc up&DN line),connection of Joc-Adra DN line with point No.126A & also connection of X-over point No. 133A-133B have been done on 27.5.22 during 1stday of NIwork of Adra which improve Train operation.
Day...
more...
Day 1 - Dismantling of old X-over No.105A&105B with linking of X-over 132A&132B(Adra-Joc up&DN line),connection of Joc-Adra DN line with point No.126A & also connection of X-over point No. 133A-133B have been done on 27.5.22 during 1stday of NIwork of Adra which improve Train operation.