Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt

RailCal app

site support

Gour Express: আমের শহর মালদা থেকে রোজ যায় শিয়ালদা - Joydeep Roy

Search Forum
<<prev entry    next entry>>
Blog Entry# 5482949
Posted: Sep 21 2022 (15:58)

No Responses Yet
Info Update
28699 views
1

Sep 21 2022 (15:58)   KPV/Kashipur Junction (3 PFs)
sparshsinghal2110
sparshsinghal2110   640 blog posts
Entry# 5482949            Tags   Past Edits
#update2
Electrification progress on Lalkuan - kashipur route
Lalkuan - Gularbhoj outer :- Foundation work complete, Poles erected, brackets placed and wiring not done. I’m not update with the electrification of that area because of jungle area.
Gularbhoj outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring done.
Kashipur
...
more...
:- Foundation work complete, Poles erected, brackets placed and wiring not done.

Lalkuan - Kashipur route SSP details:-
Gularbhoj SSP completed
Bazpur SSP completed.
Kashipur SSP work has not started.

Note :-
I don’t know about the status of Lalkuan to Gularbhoj wether wiring has done or not l. If anyone from that side can tell than update here about the status than all the work of electrification is completed in this section

Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy