List of sections marked for possible upgradation to the MPS of 130 kmph( raising of Sectional Speed to 130 KMPH) in the current financial year i.e.. 2023-24.
PS : RB has asked for the feasibility report and line of action to be taken for the same.
PS : RB has asked for the feasibility report and line of action to be taken for the same.
35 Posts
trivandrum kozhikkode via allp is 400 kms, which is what is mentioned. but kottayam would be more beneficial considering the soil conditions, the usability, and other aspects.
But valavum thirivum kooduthal alle,Curve mattanekil task aavule,Porathenn LA issues. Not to mention the huge curve at Kollam.
qln curve is now 30 [earlier 15]. considering trains will stop there for sure there is no ,much use in further speed enhancement there. on the kyj side it is good no problems, so pickup towards kyj or deceleration at qln wouldnt affect things much.
allp or ktym, curve or soil conditions are part of kerala geography; so it cant be dealt with differently in allp or ktym. both would be same only. allp is still single while ktym is fedl. that can bring in a change like vb did.
allp or ktym, curve or soil conditions are part of kerala geography; so it cant be dealt with differently in allp or ktym. both would be same only. allp is still single while ktym is fedl. that can bring in a change like vb did.