Superfast12121 89 blog postsIf the entire route is electrified, any idea why this train is a end to end diesel haul ?
7 Posts
After CRS/PCEE inspection, until CRS/PCEE gives a nod, eloco operations cannot start. Same is the case here. The officers might have found flaws or the report may not be out yet (in the report they mention what are the flaws and if it is fit for eloco run or not).
They had better. Else they will have to rectify the flaws at their cost if flaws were detected from the set construction standards.
Agree. Do you have access to any such guidelines for commissioning of electric sections ?