Blog Entry# 5859476
Posted: Oct 22 2023 (21:35)

No Responses Yet
Info Update
42215 views
5

Oct 22 2023 (21:35)   NIRA/Nira (1 PFs)
hrid22~
hrid22~   12678 blog posts
Entry# 5859476            Tags  
3 compliments
Useful Useful Useful
#Admin #Moderator Source Cr X Handle
#CRInfraUpdates
*Pune-Miraj section Doubling*

Nira-Lonand 7.64 km section doubling-
Completed
...
more...
& commissioned for traffic today 22/10/23 with successful speed trial of 117 kmph and inspection of new track & track safe certification by CRS (Commissioner of Railway Safety) Shri. Manoj Arora and Chief Administrative Officer (construction) Shri Vivek Kumar Gupta.

CR has completed 137.67 km multitracking (doubling/3rd/4th line/new line) in current FY from April'23 to till date 2023

➡️Total Length-279.05 km
➡️Completed doubling- 174.85 km (62.65%)
➡️Total Cost- 4882.53 Crs
➡️Expenditure till date- 3200 Crs (65.53%)
➡️Overall physical progress- 86%
➡️Land Acquisition completed- 97.04 Hectare/115 Hectare (84.38%).

🟢Completed sections-
174.78 km (62.65%)
Pune-Shindawane
Ambale-Adarki
Palsi-Jarandeshwar
Satara-Koregaon
Sangli-Shenoli

🟡Near completion sections-
(Likely in this Fin.Year)-
73.70 km (26.41%)
Palsi-Adarki
Satara-Jarandeshwar
Shenoli-Targaon
Sangli-Miraj

🟠In progress-
30.50 km (10.86%)-
Ambale-Shindawane
Targaon-Koregaon

🟢Completed works-
✅Earthwork-2.85 Crs Cum/3.29 Crs Cum (86%)
✅Blanketing- 17 Lcum/36.5 Lcum (47%)
✅Major bridges- 57/75 (76%)
✅Minor bridges/RUB- 365/484 (75%)
✅ROB- 7/10 (70%)
✅Tunnels- 2.6/3
-Saphale-Adarki 274 mtr tunnel completed
-Adarki-Wathar 169 mtr tunnel completed
-Ambale-Shindawane- 110 mtr tunnel in progress
✅Tunnel lengths completed- 475/553 mtr (86%)
✅Station buildings- 29/32
✅Track linking- 200 km/280 km
✅Signalling Electronic interlocking- 22/32 stations
✅OHE Electrification- 151/280 km

Completion of this doubling will improve mobility of trains on Pune-Miraj busy route & will reduce congestion.

Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy