Mar 22 (16:46) Atlas Track# 896.19 Atlas - Track Type
SG Railfan JBP IND
SGRFC^~ 168 Conf TLs 106 Void TLsRoute: 896 SEGM/Sewagram Junction - SNI/Sindi: Construction - Electric-Line Quadrupling: 0 km/h
2 Posts
If tripling+ quadrupling is done then also only tripling to be updated.
Quadrupling is to be updated only when triple lines are commissioned.
There is no option to update tripling+ quadrupling as of now.
Quadrupling is to be updated only when triple lines are commissioned.
There is no option to update tripling+ quadrupling as of now.
It will be updated together.
Khapri Nagpur tripling+quadrupling is almost completed, anytime CRS will happen.
If possible, I will visit khapri outer to show the progress .
Please refer SECR N CR railfan YouTube channel
Khapri Nagpur tripling+quadrupling is almost completed, anytime CRS will happen.
If possible, I will visit khapri outer to show the progress .
Please refer SECR N CR railfan YouTube channel
Third and fourth line together will be commissioned after CRS. see these videos
As per site guidelines Im saying.
Updating quadrupling means third line is commissioned.
Once both are completed together then update quadrupling ines directly.
Updating quadrupling means third line is commissioned.
Once both are completed together then update quadrupling ines directly.