Finally Goods train with ELoco ran successfully on KTE-JBP electrfied section.
And also railway officials confirmed that we can see passenger trains with ELoco from 20th September.
And the other news coming from Katni Murwara junction is that platform shed work is on progress
Coach display indicators will be installed after shed work.
And...
more...
And also railway officials confirmed that we can see passenger trains with ELoco from 20th September.
And the other news coming from Katni Murwara junction is that platform shed work is on progress
Coach display indicators will be installed after shed work.
And...
more...
2 Public Posts - Wed Sep 12, 2018
2 Public Posts - Thu Sep 13, 2018
So here is the official stamp for Eloco in KTE-JBP newly electrified section.
As officials confirm that Goods loco will be on track from first week of September and Passenger loco will be on track from 20th September.
But the second news from katni is totally different as NKJ-KMZ flyover is causing a difficulty in electrfication.
Height of bridge is not safe for electrfication...
more...
As officials confirm that Goods loco will be on track from first week of September and Passenger loco will be on track from 20th September.
But the second news from katni is totally different as NKJ-KMZ flyover is causing a difficulty in electrfication.
Height of bridge is not safe for electrfication...
more...
28 Public Posts - Tue Sep 04, 2018
Finally the date for CRS is out now.
CRS of Newly electrified JBP-KTE route will be take place on 20th augast.
After successful CRS inspection Goods trains may be on tracks from 20th augast on trial basic after that passenger trains will get ELoco.
#electrification
...
more...
CRS of Newly electrified JBP-KTE route will be take place on 20th augast.
After successful CRS inspection Goods trains may be on tracks from 20th augast on trial basic after that passenger trains will get ELoco.
#electrification
...
more...
7 Public Posts - Fri Aug 17, 2018
2 Public Posts - Sat Aug 18, 2018
Finally electric loco came on tracks of JABALPUR-KATNI section
Todays Bhaskar said that Trial run of electric loco between Jabalpur to Dundi was successful.
No fault has been found on entire 60 km route
Everything was fine.
...
more...
Todays Bhaskar said that Trial run of electric loco between Jabalpur to Dundi was successful.
No fault has been found on entire 60 km route
Everything was fine.
...
more...