Progress update of #PuneMetro Reach-1 - PCMC-Range Hills
⏺️Total 237 segments are launched for viaduct
⏺️148 pillars with 69 pier caps are completed
⏺️188 footings are done & excavation in progress
⏺️Also, pillar foundation...
more...
⏺️Total 237 segments are launched for viaduct
⏺️148 pillars with 69 pier caps are completed
⏺️188 footings are done & excavation in progress
⏺️Also, pillar foundation...
more...
7 Public Posts - Tue Aug 28, 2018
#PuneMetro Update of Vanaz - Civil Court Route:
⏺️Launching girder work in progress at Anand Nagar along with piers for station
⏺️Foundation of pillars work now reached till More Vidyalaya
⏺️Pier caps ready near Krishna Hospital
For...
more...
⏺️Launching girder work in progress at Anand Nagar along with piers for station
⏺️Foundation of pillars work now reached till More Vidyalaya
⏺️Pier caps ready near Krishna Hospital
For...
more...
First span completed at Phugewadi near Mega Mart for #PuneMetro Reach 1 PCMC- Range Hills with the help assembly of Ground Support Trestle while segment launching for 2nd span is in progress. Along with this other piers are also getting ready.
For viewing images related to this topic and source click here
For viewing images related to this topic and source click here
#PuneMetro work for Reach 2 on the Karve road has now started. Second segment has been launched on the second pillar at Anand Nagar. Soon the span will be erected.
Source: click here
Source: click here
#PuneMetro: Update on Tree Transplantation, A green initiative taken by Pune Metro. 125 trees were transplanted at different areas. It included Ashokas, Palm trees, two big trees, etc.
They are transplanted at STP Plant Kasarwadi, Rose Garden, Akurdi, PCMC ground and Mutha river bed.
For viewing related images & Source: click here
They are transplanted at STP Plant Kasarwadi, Rose Garden, Akurdi, PCMC ground and Mutha river bed.
For viewing related images & Source: click here