#ElectrificationUpdate #25February2020
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
CRS inspection from DAL/DaliGanj Junction has started at 10:30AM with 10 coaches train which was hauled by GD WDM3A 14061R diesel loco. After departing from DAL/DaliGanj Junction CRS special train reached SD/Sidhauli where light snacks was arranged but team didn't had due to time constrain and moved to KMP/Kamlapur where lunch was served. After lunch inspection convoy moved towards STP/Sitapur Junction and reached around 05:30PM. After inspecting RE at STP/Sitapur Junction for around 1 hour inspection train departed STP/Sitapur Junction around 06:30PM for...
more...
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
CRS inspection from DAL/DaliGanj Junction has started at 10:30AM with 10 coaches train which was hauled by GD WDM3A 14061R diesel loco. After departing from DAL/DaliGanj Junction CRS special train reached SD/Sidhauli where light snacks was arranged but team didn't had due to time constrain and moved to KMP/Kamlapur where lunch was served. After lunch inspection convoy moved towards STP/Sitapur Junction and reached around 05:30PM. After inspecting RE at STP/Sitapur Junction for around 1 hour inspection train departed STP/Sitapur Junction around 06:30PM for...
more...
2 Public Posts - Tue Feb 25, 2020
1 Public Posts - Wed Feb 26, 2020
#ElectrificationUpdate #25February2020
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
CRS inspection about to begin from DAL/DaliGanj...
PC : Ratan Sharga
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
CRS inspection about to begin from DAL/DaliGanj...
PC : Ratan Sharga
2 Public Posts - Tue Feb 25, 2020
#ElectrificationUpdate #24February2020
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Finally the "D" day has come
On 09Feb2019 LJN DRM Shrimati Vijaykaushik has laid foundation of first electric pole foundation near MBP/Mohibullapur railway station and after a year on 14Jan2020 first electric loco (GD WAG7 27210) trial run was successfully completed.
After...
more...
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Finally the "D" day has come
On 09Feb2019 LJN DRM Shrimati Vijaykaushik has laid foundation of first electric pole foundation near MBP/Mohibullapur railway station and after a year on 14Jan2020 first electric loco (GD WAG7 27210) trial run was successfully completed.
After...
more...
1 Public Posts - Mon Feb 24, 2020
#ElectrificationUpdate #30January2020
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 100%
Brackets - 100%
Wiring - 100%
OHE...
more...
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 100%
Brackets - 100%
Wiring - 100%
OHE...
more...
1 Public Posts - Mon Feb 03, 2020
Jan 30 2020 (10:59) 10107/Madgaon - Mangaluru Central MEMU Express | UD/Udupi (2 PFs)
DeepakUlli~
DeepakUlli~ 2929 blog postsMao - MAQ RE status update :
No RE work can be seen btn MAO - Gokarna RD
1. OHE foundation seen after Gokarna Rd
2. OHE portal can be seen at Kumta
3.OHE...
more...
No RE work can be seen btn MAO - Gokarna RD
1. OHE foundation seen after Gokarna Rd
2. OHE portal can be seen at Kumta
3.OHE...
more...
1 Public Posts - Thu Jan 30, 2020