#electrification #Patiala #Jakhal The foundation stone for electrification of Jakhal-Dhuri-Ludhiana shall be laid in last week of December 2015, and for Rajpura-Patiala-Dhuri-Lehra Mohabat , it shall be laid in January 2016.
As mentioned earlier, Rajpura-Patiala-Dhuri-Lehra Mohabat got delayed over a month cuz of FLS and other related works like planning for doubling.
As mentioned earlier, Rajpura-Patiala-Dhuri-Lehra Mohabat got delayed over a month cuz of FLS and other related works like planning for doubling.
9 Public Posts - Sun Nov 22, 2015
The section from HSR-LDH shall take near 30 months. Regarding starting of new trains, firstly all these 3 section s are being developed keeping in view of smooth freight operations cuz of DFC and also for decongesting the existing routes which are running over capacity. The period or TDC for Rajpura-Patiala-Dhuri-Lehra Mohabat is also 30 months. so, i believe these sections shall be fully commissioned at the same time.
6 Public Posts - Sun Nov 22, 2015
1 Public Posts - Mon Nov 23, 2015
2 Public Posts - Thu Nov 26, 2015
1 Public Posts - Fri Nov 27, 2015
3 Public Posts - Fri Dec 04, 2015
2 Public Posts - Sun Dec 20, 2015
1 Public Posts - Wed Dec 23, 2015