GC update of STP-MLN section..After the completion of ASH-STP GC NER along with RVNL focusing more on this section.. Track packing machine will now cover from Sitapur JN to Mailani JN. It will take near about 3months to cover 106km so from February freight trains trial will start running and all the station work will be completed by December so we can expect CRS in the month of April and commencement on this section in June 2019.
11 Public Posts - Thu Oct 25, 2018
1 Public Posts - Fri Oct 26, 2018
LJN-BE via BLM-SPN ka kuch trains ab LJN-DAl-STP-SPC-SPN hoke jayega sayad. Also BLM mein Yard remodelling, NI/Pre Ni work hoga taki ON se SPN janewale CNB-JAT Barfaani Exp & CNB-ASR Beas Ganga Exp ka BLM mein reversal avoid kiya ja sake