Search Forum
Blog Entry# 3936040
Posted: Oct 25 2018 (09:34)
17 Responses
Last Response: Oct 29 2018 (22:32)
17 Responses
Last Response: Oct 29 2018 (22:32)
GC update of STP-MLN section..After the completion of ASH-STP GC NER along with RVNL focusing more on this section.. Track packing machine will now cover from Sitapur JN to Mailani JN. It will take near about 3months to cover 106km so from February freight trains trial will start running and all the station work will be completed by December so we can expect CRS in the month of April and commencement on this section in June 2019.
11 Public Posts - Thu Oct 25, 2018
2 Public Posts - Fri Oct 26, 2018
Abhi tak toh aisa kuch plan nhi hai.. In future agar aisa hota Hai toh kafi time save hoga.. Loco reversal(Diesel-electric) me abhi 30-45min lag jate.. Woh time kafi Kam ho jayega isse.
1 Public Posts - Sat Oct 27, 2018
2 Public Posts - Mon Oct 29, 2018