Search Forum
Blog Entry# 4072350
Posted: Dec 05 2018 (23:48)
5 Responses
Last Response: Dec 11 2018 (15:45)
5 Responses
Last Response: Dec 11 2018 (15:45)
Dec 05 2018 (23:48) 14241/Nauchandi Express | ALD/Allahabad (10 PFs)
highvoltageeee2k3~
highvoltageeee2k3~ 447 blog postsquestion guys, what are the doubling projects currently being executed in uttar pradesh.
LKO-FD-JNU is 60 percent doubled...
LKO-PBH-JNH is 80 percent doubled...
JNH-BSB doubling now done..
ALD-ALY-MUV-BSB only ground levelling done..
CNB-JHS 60-70 percent done..
ALD-PFM...
more...
LKO-PBH-JNH is 80 percent doubled...
JNH-BSB doubling now done..
ALD-ALY-MUV-BSB only ground levelling done..
CNB-JHS 60-70 percent done..
ALD-PFM...
more...
4 Public Posts - Tue Dec 11, 2018