Updates Regarding Electrification:
The Entire Electrification work has been Completed b/w Kiul - jmp Including wiring done fully...And The wiring 80% Completed In Jmp - Bgp Route the wiring has been done From Before Patam till Muslim school...But the substation work is still going on b/w Jmp and bgp I hope ki Atleast April ya May tk Bgp Tk Full Electrified Hojyega...I think Jmp - Kiul ka Electric Trial February ke 2nd week mhe krlena chaiye the only problem of Electrification After Jmp Station...And rest all are set...Btw Give ur suggestion regarding any update that i missed..!!
The Entire Electrification work has been Completed b/w Kiul - jmp Including wiring done fully...And The wiring 80% Completed In Jmp - Bgp Route the wiring has been done From Before Patam till Muslim school...But the substation work is still going on b/w Jmp and bgp I hope ki Atleast April ya May tk Bgp Tk Full Electrified Hojyega...I think Jmp - Kiul ka Electric Trial February ke 2nd week mhe krlena chaiye the only problem of Electrification After Jmp Station...And rest all are set...Btw Give ur suggestion regarding any update that i missed..!!
No substation work began at Bhagalpur Jn is matter of concern to start electrification in march. Meet me next tym when you come BhagalpurJn till Jan just mutual meeting most of RF of our region have already met it's your wish if you interested to share throughts comming from same area.
Power sub station work progress jamalpur is very slow.cant say anything what will happen in february ?