Electrification Completed of Q1 Target :
.
SC unit : 57/90 km 64%
UMB unit : 49/115 km 42%
LKO unit : 94/278 km 34%
JP...
more...
.
SC unit : 57/90 km 64%
UMB unit : 49/115 km 42%
LKO unit : 94/278 km 34%
JP...
more...
5 Public Posts - Sat Jun 29, 2019
7 Public Posts - Sun Jun 30, 2019
2 Public Posts - Tue Jul 02, 2019
1 Public Posts - Wed Jul 03, 2019
Mast erection started by Rail Crane in Samakhyali - Gandhidham section of Ahemdabad division of Western Railway as a part of Electrification by RE Ahemdabad project unit for introduction of Electric Traction.
source CORE
source CORE