SWR targets for commissioning of sections in FY 2019-20
Newline
1.Gangavath- karatagi =27.5km part of Ginigera Raichur new line target by Dec 2019 (likely to miss).
2.Baiyappanahalli's 3rd terminal target was July 2019 missed new target is march 2020.
Doubling...