Dec 20 2020 (10:01) 08463x/Prasanti Express Special | YNK/Yelahanka Junction (5 PFs)
MywayRailway~
MywayRailway~ 715 blog postsMakalidurga - Yelahanka Doubling works Final stage of Doubling
2 Posts
Except at Yelahanka yard remodeling and Yelahanka to rajanukunte doubling track remaining works like interlocking around Rajanukunte,dodballapur , oddarahalli got completed
Doubling itself won't take much time. But looking at the amount of work it looks like they will do at YNK (yard as well as station remodeling), a CRS inspection may take some more time.
maybe the will use this lean period to finish all pending works
In the video u can see at oddarahalli train running on new track,and in most stations Interlocking works done