Pune Satara section Doubling Updates
1) Alandi Shindwane
Doubling done
CRS done on 26 Dec 2020
Line to be opened from 1 Jan 2021
...
more...
2) Shindawane Ambale
Rock cutting :- 90% done
Viaducts Pillers construction in progress
Doubling in this ghat section will take time(minimum 7-8 months)
3) Ambale Rajevadi
Track laying in progress
CRS to likely happen by Jan 2021 mid or end
95% track laying done
4) Rajewadi Jejuri
Pillars are constructed on some small nalas and rivers
Blanket is ready for track laying except incomplete small bridges
70% Doubling done
date to be decided for commissioning
5) Jejuri Daundaj
Blanketing in progress
6) Daundaj Valha
It's Double line
Operational
7) Valha nira
Track laying to start soon
expecting CRS in February 21
8) Nira Lonand
Ground Leveling work in some sections and Blanketing work also
9) Lonand Adarki
Blanket work is going on
Adarki Tunnel work 90% completed
10) Adarki Wathar
Ground Leveling and Blanketing in progress
11) Wathar Satara
Not too much progress