what is the update of doubling work on raikabagh merta section?? is it still in progress or stopped with lockdown??
7 Posts
yesterday (28/06/2021) travelled in marudhar special from ju to kuchaman, got the chance to see doubling work..it is at full progress except the section between banaar(some distance before banaar stn) and jajiwal. no work in this section. after merta to kuchaman in more then 50% section tracks are laid down.
There is issue from Indian Army between Banar and Jajiwal, thats y there is no doubling work in progress