Mahabubnagar - Gollapalli Railway Line Doubling and Electrification Status Part of Secundebad - Mahabubnagar Doubling & Electrification Project
Do you know the CRS date for mbnr-divitipalli
Also, you have mentioned March,2022 is the target but jcl-gollapalli works seem to be struck for long time, do you know the reason?
Also, you have mentioned March,2022 is the target but jcl-gollapalli works seem to be struck for long time, do you know the reason?
1st pf@jcl will be mainline towards kcg as SCR is planning to construct new loopline and that will be 1st pf, may for that sake jcl - gollapalli line is getting delayed also bridge work
yeah but they are taking longer time for this, if they just finish works at JCL station then except divitialli flyover all works are done