Vijayawada-Gudur 3rdline update
40 km :Chirala to karavadi (10 km before ongole) thirdline work in full swing, just new platform and interlocking, 95% tracks laid,2-3 bridges small patches and some 10 km electrification needed by 3-6 months or year end 40 km line soon will be on tracks (I have seen from 6.15-6.53 am only) bza-chirala outer no idea.
From karavadi to ongole no progress
40 km :Chirala to karavadi (10 km before ongole) thirdline work in full swing, just new platform and interlocking, 95% tracks laid,2-3 bridges small patches and some 10 km electrification needed by 3-6 months or year end 40 km line soon will be on tracks (I have seen from 6.15-6.53 am only) bza-chirala outer no idea.
From karavadi to ongole no progress