कोंकण रेल्वे का electric loco trarctiony change program postpone क्यूँ होगया?
4 Posts
October 2022 targeted.Tss work completed.But incoming transmission line work on progress.Ratnagiri Tss also targeted to complete in this month and Kharepatan tss targeted on September 2022.
If that is the case why did KR issued a PR saying compete electrification of KR and also running of few initial rake with electric traction. Means until October November passenger trains will not run with elco.
How is it that freight trains are running with e-locos even with TSS work not completed at said locations?
They tried to extend Thivim tss supply.Bcoz of Balli tss yet to energise.But this not worked.That why 1st phase train didn't run with E loco