Bengaluru to Hubballi railway line is now fully Doubled and Electrified
Hurdles to start Vande Bharat express have now been cleared
Read more: click here
Hurdles to start Vande Bharat express have now been cleared
Read more: click here
2 Posts
Even Kurnool-Gadwal is also electrified. With this... Dhone-Kacheguda line is completely electrified.
So, KSK (12649/50) and Kacheguda SF (12785/6) could be given eloco end to end..
So, KSK (12649/50) and Kacheguda SF (12785/6) could be given eloco end to end..
KSK has been getting delayed all these days due to the works that have been going on SBC-Hubli section.... not because of loco change...
Now it should run ontime hopefully....
Now it should run ontime hopefully....
KSK is mostly gets late at UBL station & in between UBL-GDG stretch, which has nothing to do with SBC_UBL doubling.
It could take another 6 months-1year. Only 2 TSS out of 8 in YPR-Hubli section are complete. Moreover, Hubli shed has 0 WAP7s. Whatever KJM shed has it's not enough, as SWR is having eloco shortages. For now, vande bharat can run between SBC-UBL I guess.