The doubling between Betamcherla and B Cement Nagar was completed and commissioned. CRS inspection was carried out on 27.03.24. #moderator #admin please update in atlas.
3 Posts
So with this now only Giddalur to B cement nagar remains a single line ??
Any idea about doubling progress there and when those can be commissioned ?
Any idea about doubling progress there and when those can be commissioned ?
Panyam to Nandyala will be end of December. Nandyala to gazulapalli works not started
By the end of April, giddalur-diguvametga will be completed. By July end, b cement nagar to panyam can be completed. By December/January panyam to Nandyala can be completed. Remaining will be in next financial year only