Work: 95 Km ЁЯМЙBridges: 3 Important Rail Bridges, 3 Road Bridges and 15 minor bridges completed. тЫ░я╕П6 Breakthrough of 15.3 km completed Source: MOR Twitter Handle
First breakthrough in excavation of T-12 Main Tunnel of 1,987.50 m, between Dungripanth-Narkota has been achieved, completing 2/4 drives in T-12, accomplishing total tunnelling progress of 72 km of 213 km on the Project.
рдирдордГ рджреЗрд╡рднреВрдорд┐ рдирдордГ The Rishikesh-Karnaprayag Rail Line Project achieved the first breakthrough in the excavation of Tunnel 12 - Escape Tunnel of length 1965.50 m. click here
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.