#CRupdate on Special Block for Infra upgrade work at Thane station.
HISTORIC WORK ON WIDENING OF THANE STATION's PLATFORM 5/6 COMPLETED! ... more...
• Widening of Platform 5/6 by 2-3 meters for 587 meters length • Use of 750 pre-cast hollow blocks • Coordination of 400 laborers, 20 teams, and 10 contractors • Minimal disruption despite 935 train cancellations Efficient execution with zero delays! • Work carried out along with NI work of CSMT, one of the busiest coaching terminals of Indian Railways. * Deep appreciation to the work force for their meticulous planning, precision at work and timely execution.
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.