#Admin #Moderator Source Cr X HandleKindly Update It (1/2)#CRInfraUpdatesToday 23/12/23, CR has successfully completed & commissioned 23.69 km new line section between Deoli-Kalamb section on Wardha-Nanded line.CRS (Commissioner of Railway Safety) Shri. Manoj Arora inspected the new line sections & given it's safe certificate.Speed trial of 125 kmph conducted successfully in newly opened line.Chief Administrative Officer construction/Shri. Avanish Kumar Pandey & DRM/Nagpur Shri. Tushar Kant Pandey also conducted inspection of new line.With this 23.69 km new line opening, CR has completed construction of 185.49 km of new lines/double line/3rd/4th lines in April-December 2023.❇Wardha-Nanded New line (via Yavatmal-Pusad).Nagpur div.🔸Length- 284.65 km🔸Overall Physical...
×
5805 views
0
@WR 41m late@WR: Wardha Jn &0 km/h.....
×
5805 views
0
@WR 41m late@WR: Wardha Jn &0 km/h.....
×
5805 views
0
@WR 41m late@WR: Wardha Jn &0 km/h.....
×
5805 views
0
@WR 41m late@WR: Wardha Jn &0 km/h.....
×
4484 views
0
@WR 37m late@WR: Wardha Jn &26 km/h ......Arrival done
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
28073 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟩Wardha - Nagpur 3rd/4th line ➡️Length - 78.70 km➡️Length commissioned - 34.59 km➡️Remaining - 44.11 km ➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)🪙 Cost - 1177.97 Cr🪙 Expenditure till date - 1035.92 Cr 🟩Completed doubling - 34.59 km (43.95%)A) Khapri - Sindi 🟩Near completion section- 27.14 km (34.48%)B) Sindi - Seloo Road C) Khapri - Ajni 🟩In Progress section- 16.99 km (21.58%) Seloo Road - Wardha Ajni - Nagpur ➡️Land acquisition- 36.47/36.51 Ha (99.50%) ➡️Completed works details - ➡️Earthwork - 22.39/32.63 Lcum(69%)➡️Important Bridges - 2/2 (100%)➡️Major Bridges - 10/12 (83%)➡️Minor Bridges - 70/144...
×
WR/Wardha Junction
17215 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟢 Wardha-Ballarshah New 3rd line -💰 Cost- ₹ 1384.72 Cr. 💰 Expenditure till date- ₹ 833.49 Cr.🟢Overall Physical Progress - 67%🔘 Total Length: 132.34 Km🔘 Length Commissioned - 29.35 Km🔘 Length remaining - 102.99 km 🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)A) Completed Sections: 33.33 km (25.18%)-Wardha - HinganghatB) Near Completion Sections - 47.98 km (36.25%)-Hingaghat- Chikni Road,Majri-TadaliC) In Progress Sections - 51.03 km (38.57%)-Chikni Road-Majri,Tadali-Ballarshah 🟢In Progress Works-☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)☑ Blanketing- 60000/195000 Cum completed (30.76%)☑ Important bridges– 1/2 completed. (50%)☑ Major Bridge– 6 out of 12 in Progress. ☑...
×
WR/Wardha Junction
17215 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟢 Wardha-Ballarshah New 3rd line -💰 Cost- ₹ 1384.72 Cr. 💰 Expenditure till date- ₹ 833.49 Cr.🟢Overall Physical Progress - 67%🔘 Total Length: 132.34 Km🔘 Length Commissioned - 29.35 Km🔘 Length remaining - 102.99 km 🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)A) Completed Sections: 33.33 km (25.18%)-Wardha - HinganghatB) Near Completion Sections - 47.98 km (36.25%)-Hingaghat- Chikni Road,Majri-TadaliC) In Progress Sections - 51.03 km (38.57%)-Chikni Road-Majri,Tadali-Ballarshah 🟢In Progress Works-☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)☑ Blanketing- 60000/195000 Cum completed (30.76%)☑ Important bridges– 1/2 completed. (50%)☑ Major Bridge– 6 out of 12 in Progress. ☑...
×
WR/Wardha Junction
17215 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟢 Wardha-Ballarshah New 3rd line -💰 Cost- ₹ 1384.72 Cr. 💰 Expenditure till date- ₹ 833.49 Cr.🟢Overall Physical Progress - 67%🔘 Total Length: 132.34 Km🔘 Length Commissioned - 29.35 Km🔘 Length remaining - 102.99 km 🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)A) Completed Sections: 33.33 km (25.18%)-Wardha - HinganghatB) Near Completion Sections - 47.98 km (36.25%)-Hingaghat- Chikni Road,Majri-TadaliC) In Progress Sections - 51.03 km (38.57%)-Chikni Road-Majri,Tadali-Ballarshah 🟢In Progress Works-☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)☑ Blanketing- 60000/195000 Cum completed (30.76%)☑ Important bridges– 1/2 completed. (50%)☑ Major Bridge– 6 out of 12 in Progress. ☑...
×
WR/Wardha Junction
17215 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟢 Wardha-Ballarshah New 3rd line -💰 Cost- ₹ 1384.72 Cr. 💰 Expenditure till date- ₹ 833.49 Cr.🟢Overall Physical Progress - 67%🔘 Total Length: 132.34 Km🔘 Length Commissioned - 29.35 Km🔘 Length remaining - 102.99 km 🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)A) Completed Sections: 33.33 km (25.18%)-Wardha - HinganghatB) Near Completion Sections - 47.98 km (36.25%)-Hingaghat- Chikni Road,Majri-TadaliC) In Progress Sections - 51.03 km (38.57%)-Chikni Road-Majri,Tadali-Ballarshah 🟢In Progress Works-☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)☑ Blanketing- 60000/195000 Cum completed (30.76%)☑ Important bridges– 1/2 completed. (50%)☑ Major Bridge– 6 out of 12 in Progress. ☑...
×
WR/Wardha Junction
17215 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟢 Wardha-Ballarshah New 3rd line -💰 Cost- ₹ 1384.72 Cr. 💰 Expenditure till date- ₹ 833.49 Cr.🟢Overall Physical Progress - 67%🔘 Total Length: 132.34 Km🔘 Length Commissioned - 29.35 Km🔘 Length remaining - 102.99 km 🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)A) Completed Sections: 33.33 km (25.18%)-Wardha - HinganghatB) Near Completion Sections - 47.98 km (36.25%)-Hingaghat- Chikni Road,Majri-TadaliC) In Progress Sections - 51.03 km (38.57%)-Chikni Road-Majri,Tadali-Ballarshah 🟢In Progress Works-☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)☑ Blanketing- 60000/195000 Cum completed (30.76%)☑ Important bridges– 1/2 completed. (50%)☑ Major Bridge– 6 out of 12 in Progress. ☑...
×
WR/Wardha Junction
17215 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟢 Wardha-Ballarshah New 3rd line -💰 Cost- ₹ 1384.72 Cr. 💰 Expenditure till date- ₹ 833.49 Cr.🟢Overall Physical Progress - 67%🔘 Total Length: 132.34 Km🔘 Length Commissioned - 29.35 Km🔘 Length remaining - 102.99 km 🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)A) Completed Sections: 33.33 km (25.18%)-Wardha - HinganghatB) Near Completion Sections - 47.98 km (36.25%)-Hingaghat- Chikni Road,Majri-TadaliC) In Progress Sections - 51.03 km (38.57%)-Chikni Road-Majri,Tadali-Ballarshah 🟢In Progress Works-☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)☑ Blanketing- 60000/195000 Cum completed (30.76%)☑ Important bridges– 1/2 completed. (50%)☑ Major Bridge– 6 out of 12 in Progress. ☑...
×
WR/Wardha Junction
17215 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟢 Wardha-Ballarshah New 3rd line -💰 Cost- ₹ 1384.72 Cr. 💰 Expenditure till date- ₹ 833.49 Cr.🟢Overall Physical Progress - 67%🔘 Total Length: 132.34 Km🔘 Length Commissioned - 29.35 Km🔘 Length remaining - 102.99 km 🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)A) Completed Sections: 33.33 km (25.18%)-Wardha - HinganghatB) Near Completion Sections - 47.98 km (36.25%)-Hingaghat- Chikni Road,Majri-TadaliC) In Progress Sections - 51.03 km (38.57%)-Chikni Road-Majri,Tadali-Ballarshah 🟢In Progress Works-☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)☑ Blanketing- 60000/195000 Cum completed (30.76%)☑ Important bridges– 1/2 completed. (50%)☑ Major Bridge– 6 out of 12 in Progress. ☑...
×
WR/Wardha Junction
17215 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟢 Wardha-Ballarshah New 3rd line -💰 Cost- ₹ 1384.72 Cr. 💰 Expenditure till date- ₹ 833.49 Cr.🟢Overall Physical Progress - 67%🔘 Total Length: 132.34 Km🔘 Length Commissioned - 29.35 Km🔘 Length remaining - 102.99 km 🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)A) Completed Sections: 33.33 km (25.18%)-Wardha - HinganghatB) Near Completion Sections - 47.98 km (36.25%)-Hingaghat- Chikni Road,Majri-TadaliC) In Progress Sections - 51.03 km (38.57%)-Chikni Road-Majri,Tadali-Ballarshah 🟢In Progress Works-☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)☑ Blanketing- 60000/195000 Cum completed (30.76%)☑ Important bridges– 1/2 completed. (50%)☑ Major Bridge– 6 out of 12 in Progress. ☑...
×
WR/Wardha Junction
17215 views
5
#Admin #Moderator Source Cr X Handle#CRInfraUpdates🟢 Wardha-Ballarshah New 3rd line -💰 Cost- ₹ 1384.72 Cr. 💰 Expenditure till date- ₹ 833.49 Cr.🟢Overall Physical Progress - 67%🔘 Total Length: 132.34 Km🔘 Length Commissioned - 29.35 Km🔘 Length remaining - 102.99 km 🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)A) Completed Sections: 33.33 km (25.18%)-Wardha - HinganghatB) Near Completion Sections - 47.98 km (36.25%)-Hingaghat- Chikni Road,Majri-TadaliC) In Progress Sections - 51.03 km (38.57%)-Chikni Road-Majri,Tadali-Ballarshah 🟢In Progress Works-☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)☑ Blanketing- 60000/195000 Cum completed (30.76%)☑ Important bridges– 1/2 completed. (50%)☑ Major Bridge– 6 out of 12 in Progress. ☑...
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.