Jiribam-Imphal, Manipur Project Progress Report:1) 89.20% of work completed2) Tunnels- 48 of 52 completed3) Bridges:- Major: 11; substructure of 7and superstructure of 5 completed- Minor: 101 of 129 completed4) Stations: 6 of 11 constructed click here
×
JRBM/Jiribam
19911 views
1
Jiribam-Imphal, Manipur Project Progress Report:1) 89.20% of work completed2) Tunnels- 48 of 52 completed3) Bridges:- Major: 11; substructure of 7and superstructure of 5 completed- Minor: 101 of 129 completed4) Stations: 6 of 11 constructed click here
×
JRBM/Jiribam
19911 views
1
Jiribam-Imphal, Manipur Project Progress Report:1) 89.20% of work completed2) Tunnels- 48 of 52 completed3) Bridges:- Major: 11; substructure of 7and superstructure of 5 completed- Minor: 101 of 129 completed4) Stations: 6 of 11 constructed click here
×
JRBM/Jiribam
19911 views
1
Jiribam-Imphal, Manipur Project Progress Report:1) 89.20% of work completed2) Tunnels- 48 of 52 completed3) Bridges:- Major: 11; substructure of 7and superstructure of 5 completed- Minor: 101 of 129 completed4) Stations: 6 of 11 constructed click here
×
JRBM/Jiribam
12205 views
1
For enhancing safety and efficiency in train operation, NFR today commissioned a new Electronic Interlocking system at Jiribam station in Manipur @RailMinIndia @AmritMahotsav click here
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.