yesterday traveled in this section and here is the doubling progress
1. mbnr-divitipalli doubling is almost over - hardly it takes 1 month to finish the works 2.divitipalli-jcl -- It may take at least 6 months as highway bridge alignment needs to modified 3.... more...
jcl-gollapllalli- works are almost over except near jcl station and removing one manned crossing
So overall, by march we can except entire sc-mbnr as FEDL except jcl-divitipalli
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.