Update on #Electrification of Rajpura-Patiala-Dhuri-Lehra Mohabat. Work as of today.
2 Posts
YA, they are doing it from Rajpura end. In next 10-15 days, they'll reach Kauli. RVNL is adding more gang so that each gang shall be given 3-4 sections. They have constructed near 70 foundations over 7 km of distance and once they exceed 100, the mast erecting team shall start from Rajpura end with Mast Erecting Vehicle .
Simultaneously, doubling is also going to start here soon. The work is with Northern Railway Construction Organization, they'll do the electrification of the 2nd line simultaneously.