#ETALDELECTRIFICATION
In a nutshell, I've closely identified the progress of electrification work between Jabalpur and Itarsi. The details are given below.
1. Jabalpur (excl.)-Narsinghpur work is almost done. Wiring is complete. Work left is only on the two bridges over Narmada river. I think they are deciding to electrify KEQ-JBP at the end. Pic is given in my trip blog.
2. The pic...
more...
In a nutshell, I've closely identified the progress of electrification work between Jabalpur and Itarsi. The details are given below.
1. Jabalpur (excl.)-Narsinghpur work is almost done. Wiring is complete. Work left is only on the two bridges over Narmada river. I think they are deciding to electrify KEQ-JBP at the end. Pic is given in my trip blog.
2. The pic...
more...
7 Public Posts - Fri Dec 23, 2016
4 Public Posts - Sat Dec 24, 2016
This is a big and owesom news update that work progress has started between gadarwada and pipariya it was not expected anytime soon i lost hope of any progress till 2018 but it looks like we are going to have itarsi jabalpur electrified line very soon really u have made an awesome update today waiting for this kind of update from a very very long time
Aapka bahaut bahaut shukriya thanks a lot please keep updating work between gadarwada and pipariya bcoz only this section was having no work started
Thanks...
more...
Aapka bahaut bahaut shukriya thanks a lot please keep updating work between gadarwada and pipariya bcoz only this section was having no work started