Jan 19 2018 (09:28) 14215/Ganga Gomti Express | HCP/Harchandpur (3 PFs)
purubaba.ankit~
purubaba.ankit~ 2861 blog postsPics from Doubling Electrification of lko Raibareli section at Harchandpur
How much work is done and what are the probable dates for completion
Less than 20% is done... I dont know about probable date bt i think it will take 6 to 7 months more..
OHE is set at some station and small sections of old lone and plateform construction and doubling at crossing and outers is yet to complete..
OHE is set at some station and small sections of old lone and plateform construction and doubling at crossing and outers is yet to complete..
pfm - prg k beech bridge 50% complete ho chuka aur baki pe abi tracks k lye level kiya jara h.... aur prg - ald section k beech abi kafi kaam baki ... do overbridge banne h