Hosapete - Gunda road jn (kotturu) rly line high tension wires problem details update as on 30:03:2018..there r nearly 10 wires passing a cross rly line out of which only 2 wires cleared ..2 lines work not yet started..4 lines work stopped yet to restart ..2 lines work going on ..still 45- 60days required to complete the work ..if everything goes well hopefully in the month of June passenger train may run on this hpt - kty -hrr line ..
19 Posts
220kv one , 110kv one ,33kv Three ,11kv two ..No sign of station renovation
Election season. Any promise as to when trains will start in this section?
Lifting of high tension wires got some pace ..hopefully they will complete all remaining lines in next 10days