Status of Ald Pfm doubling
Pic 1: 4 span remain to be constructed while 25 is ready on Ganga bridge doubling at Phaphamau south (Zoom the picture and see the bridge, you will notice 4 span/beam missing/ not constructed yet)
Pic 2 &3 : Ground levelling work in relation to Ald- pfm doubling and Rambagh flyover status in North and South direction of this line
Pic 1: 4 span remain to be constructed while 25 is ready on Ganga bridge doubling at Phaphamau south (Zoom the picture and see the bridge, you will notice 4 span/beam missing/ not constructed yet)
Pic 2 &3 : Ground levelling work in relation to Ald- pfm doubling and Rambagh flyover status in North and South direction of this line
kitna work hua h doubling k..?
Ye kaun sa flyover ban raha h.MNNIT.?
Ye kaun sa flyover ban raha h.MNNIT.?
Nahi near Allahabad City/Aly (Rambagh) station ke paas so that whenever train goes from Ald to Aly, jaam lag jata tha
Ald Pfm line and Ald Aly line both are only 35 mtrs apart near Aly west side. While Ald Pfm line is on bridge 6 mtrs above road, Ald Aly line is in level of road causing jaam.
This flyover known as Rambagh flyover is being constructed 12-14 metres above present road so that to go over both the above mentioned lines and remove daily jaam situation. Itstarget is October 18.
Work...
more...
Ald Pfm line and Ald Aly line both are only 35 mtrs apart near Aly west side. While Ald Pfm line is on bridge 6 mtrs above road, Ald Aly line is in level of road causing jaam.
This flyover known as Rambagh flyover is being constructed 12-14 metres above present road so that to go over both the above mentioned lines and remove daily jaam situation. Itstarget is October 18.
Work...
more...
oct/dec 18 target h ald-pfm doubling k..
prg-pfm k bich kaise chal raha h work..?
prg-pfm k bich kaise chal raha h work..?
Prg-Pfm Doubling will take time.
First the work of remaining four span at Ganga bridge will start only after monsoon.
Then this ROB and MNNIT ROB will complete in Oct/ Nov 18.
Also all the RUBs at Ald Pfm line viz CMP degree College, Kundan guest house and Allapur is to be broadened turn by turn in August by placing RCC Square boxes after...
more...
First the work of remaining four span at Ganga bridge will start only after monsoon.
Then this ROB and MNNIT ROB will complete in Oct/ Nov 18.
Also all the RUBs at Ald Pfm line viz CMP degree College, Kundan guest house and Allapur is to be broadened turn by turn in August by placing RCC Square boxes after...
more...
As I told in Jul, that during monsoon and thereafter till dec-jan, water in ganga will not recede and remaining 04 span works between pillars will remain halted and will be a hurdle in PRG-PFM section and thus it can't complete before may-jun 2019, while ald-prayag doubling can complete by dec 2018,
same thing happened, see pics
Pic1: Water still in good quantity in ganga
Pic2&5:...
more...
same thing happened, see pics
Pic1: Water still in good quantity in ganga
Pic2&5:...
more...