DeepakUlli~ 2929 blog postsHosapete- guntakal double electrification work update:as on 13/10/2018
*guntakal - hagari =electrification work successfully completed
* hargari - ballari city out limits (gtl side) only erected electrical poles are installed wiring not done
* ballari city outer limits(gtl side ) - kudutani only OHE PIT HOLES WORK GOING ON.
*...
more...
*guntakal - hagari =electrification work successfully completed
* hargari - ballari city out limits (gtl side) only erected electrical poles are installed wiring not done
* ballari city outer limits(gtl side ) - kudutani only OHE PIT HOLES WORK GOING ON.
*...