Non interlocking block . Ajmer division
Between (Palanpur - abu road)
Between (Palanpur - abu road)
14 Posts
adi kalol , Gc completion target was March 19,
but it won't complete Before June .
but it won't complete Before June .
Many planned execution on WR are well behind schedule , refer attached Annexure CRB_ WR 2018-19...Imp Patan-Bhildi NL is yet to be commissioned & ADI-Sabarmati will take longer time due to Bridge on Sabarmati River, Sabarmati -kalol will be commissioned by June..
1st project haa been done, but not commissioned for traffic
6th project commissioned
9th Project will get open for traffic till Feb end . (Ni block taken)
18 th also very near to complete, Track laying done .
Rest...
more...
6th project commissioned
9th Project will get open for traffic till Feb end . (Ni block taken)
18 th also very near to complete, Track laying done .
Rest...
more...
Patan-Bhildi is ready for CRS... some DL sections on Viramgam-Samkhyali & Samkhyali-Palanpur are also ready for CRS...
Patan bhildi is ready, hence . Thwre were Some news Regarding Diversion of Ranakpur exp from this new route .
.
.