Electrification Update. MB-CH-BE-ALJN
Almost 80% work done at kundarkhi, all pole errected even wires got streached.
I think only Sub stations SSP'S for power supply are left with.
But no sign of Sbu power station SSP'S on whole section.
Almost 80% work done at kundarkhi, all pole errected even wires got streached.
I think only Sub stations SSP'S for power supply are left with.
But no sign of Sbu power station SSP'S on whole section.
4 Public Posts - Sat Mar 23, 2019
4 Public Posts - Sun Mar 24, 2019
3 Public Posts - Mon Mar 25, 2019
1 Public Posts - Thu Mar 28, 2019
The progress at chandausi railway station was only seen on plateform 1 and 2, this means that they want to electrify mainline and immediate loop lines only so that the CRS can be done and electric traction can be put in picture ASAP.
With this amount of work, I think within 60 days, first stretch i.e., MB-CH section will be operational.
With this amount of work, I think within 60 days, first stretch i.e., MB-CH section will be operational.