Jun 05 2019 (21:03) 12807/Samata Express | VSKP/Visakhapatnam Junction (8 PFs) | VSKP/WAP-7
RVBRao~
RVBRao~ 320 blog postsIs this running with E-E Electric Loco, without any LC at R?
After commissioning of TIG-R FEDL, ECoR/SCoR needs to finally give this prestigious train the importance it deserves by implementing the following changes:
1) LHB with HOG & Antyodaya GS coaches, LHB SLR instead of EOGs to take care of UR pax
2) Should be speeded up by atleast 30-45 Mins between VSKP-R....
more...
After commissioning of TIG-R FEDL, ECoR/SCoR needs to finally give this prestigious train the importance it deserves by implementing the following changes:
1) LHB with HOG & Antyodaya GS coaches, LHB SLR instead of EOGs to take care of UR pax
2) Should be speeded up by atleast 30-45 Mins between VSKP-R....
more...
Yes , Exactly as per the information, R-TIG is not fully Double lined & also Electrification of Loop Lines are not done between R-TIG section...….//
Last stretch of Electric line is pending for CRS approval I think. Doubling looks like it'll take one more year! I wrote about what should be done after FEDL commissioning. Even with partially commissioned double line, if Samata gets E-E Electric (VSKP WAP7) , run time can be cut by atleast 30-45 Mins.
Electrification work in yards and stations not completed.. So no train plying with eloco in raipur tig section ...possibly after July - august it will start.
Speed up and halt removal can not be done until fedl work completes...
Speed up and halt removal can not be done until fedl work completes...