NI work is scheduled on 27-29 March at PBE for linking SG track.
CRS will inspect section on 30 and 31 March.
CRS will inspect section on 30 and 31 March.
Track to ek hafte pahle hi jud gaya tha par signaling, route panel aur traffic management ke kaam jo abhi SG/Shahgad tak hue tha vo PBE/Pilibhit tak pura karne ke liye NI hoga jisme signaling aur electric department wale kaam karenge. Fir PCEE inspection aur CRS hoga.
Please refer attached schedule of PCEE inspection which is scheduled tomorrow and CRS inspection is scheduled on 31st March, with this section completion all section will be BG in IZN division.