NI work is scheduled on 27-29 March at PBE for linking SG track.
CRS will inspect section on 30 and 31 March.
CRS will inspect section on 30 and 31 March.
1 Public Posts - Sat Mar 23, 2024
Track to ek hafte pahle hi jud gaya tha par signaling, route panel aur traffic management ke kaam jo abhi SG/Shahgad tak hue tha vo PBE/Pilibhit tak pura karne ke liye NI hoga jisme signaling aur electric department wale kaam karenge. Fir PCEE inspection aur CRS hoga.