What is the status of Doubling work between TPTY - KPD ( via PAK / CTO ) ?
2 Posts
But levelling work was happening sometime ago? What happened to it ?
I've zero idea mate... cause I've never heard of this project going on... sorry...😑
DPR submitted as two parts ( TPTY - PAK & PAK - KPD). Waiting for approval from Rly Board
The clearing work seen at multiple locations is to add loop lines in stations including Bmmasamudram, Ramapuram, Siddampalli, panapakam etc to facilitate train crossings.
The clearing work seen at multiple locations is to add loop lines in stations including Bmmasamudram, Ramapuram, Siddampalli, panapakam etc to facilitate train crossings.