1 Public Posts - Sat Sep 06, 2014
1 Public Posts - Sun Sep 07, 2014
What is the progress of electrification between MB- GZB , how much time they will take to complete it.
I will say that dnt get shockd if the electrification works finishes before the end of this year...ohe poles are laid on nearly 98 percent of stretch...much work done frm moradabad to gajraula gms side... ohe wires are readyto be laid...poles can be se3n erected everywhere just wiring is left...work has been significantly done on the stretch. #GZBMBElectrification
2 Public Posts - Mon Jun 23, 2014
4 Public Posts - Mon Jun 23, 2014
2 Public Posts - Wed Jun 25, 2014
CONSTRUCTION WORK OF THE NEW GARHMUKTESHWAR BRIDGE.
.
Pic 1 (Left to right) The new bridge for the UP line constructed while doubling ; the new bridge for the DOWN line whose construction started while doubling and is now heading completion ; the old Garhmukteshwar bridge that initially used to serve both the lines and presently caters to the DOWN traffic.
.
Pic...
more...
.
Pic 1 (Left to right) The new bridge for the UP line constructed while doubling ; the new bridge for the DOWN line whose construction started while doubling and is now heading completion ; the old Garhmukteshwar bridge that initially used to serve both the lines and presently caters to the DOWN traffic.
.
Pic...
more...
5 Public Posts - Fri Apr 11, 2014
Travel time is expected to be cut short slightly and only AFTER all this is done, will this section be electrified under #GZBMBElectrification .
1 Public Posts - Sat Apr 12, 2014
1 Public Posts - Fri May 09, 2014
Apr 08 2014 (20:23) 04403XX/Barauni - New Delhi Special | PKW/Pilkhua (3 PFs)
railfan.z^~
railfan.z^~ 13777 blog posts1 Public Posts - Wed Apr 09, 2014
Apr 08 2014 (19:59) 04403XX/Barauni - New Delhi Special | HKP/Hakimpur (2 PFs)
railfan.z^~
railfan.z^~ 13777 blog posts1 Public Posts - Tue Apr 08, 2014
7 Public Posts - Wed Apr 09, 2014