SCR Commissions #Electrification of 45 Route Kms between Lohogad - Washim in the State of #Maharashtra
#Electrification update: OHE of Chikjajur - Hosadurga section (30 RKM) energised and Electric loco trial completed successfully at max sectional speed (110 kmph).
Fast Track #Electrification:
Erection of masts on bridge in #Tumakuru - #Nittur section. CRS statutory inspection is planned on 19.3.2022.
Erection of masts on bridge in #Tumakuru - #Nittur section. CRS statutory inspection is planned on 19.3.2022.
The 3rd line works along with #electrification between Kavali – Sri Venkateswarapalem have been commissioned.
This decongests the saturated #Vijayawada – #Chennai route by providing a continuous stretch of 66 kms of third line in the section.
This decongests the saturated #Vijayawada – #Chennai route by providing a continuous stretch of 66 kms of third line in the section.
1 Public Posts - Wed Mar 16, 2022
SWR is fast tracking #electrification, becoming green & clean #railway:
Gadag-Holealur Double Line section (48 RKM) is targeted for CRS inspection on 27.3.2022.
Gadag-Holealur Double Line section (48 RKM) is targeted for CRS inspection on 27.3.2022.