Blog Entry# 1187549
Posted: Aug 14 2014 (12:20)

No Responses Yet
Info Update
947 views
0

Aug 14 2014 (12:20)  
 
Saurabh
Saurabh   10920 blog posts
Entry# 1187549              
Details of ongoing railway projects, viz. new railway lines, gauge conversion and doubling falling partly or fully in the State of Madhya Pradesh are as under:-
--------
S. No. Name of the Project (Length) Anticipated Cost Expenditure upto Mar., 2014 Outlay 2014-15 Present Status
NEW LINE
1. Ramganjmandi-Bhopal
...
more...
(262 km) 1226 239 20 Ramganjmandi-Jhalawar (26.5 km) completed. Land has been acquired upto km 135 from Ramgajmandi. Preliminary work have been taken up beyond Jhalawar.
.
2. Chhota Udepur-Dhar (157 km) 1347 160 35 In Chhota Udepur-Ambari (32 km) section, Earthwork and bridge works have been taken up, except in 16.57 hectare land which has not been handed over by State
Government due to public agitation.
.
3. Dahod-Indore via Sardarpur, Jhabua and Dhar (201 km) 1640 196 70 Earthwork, bridge work, etc. have been taken up on Dahod-Katwara and Sagor-Indore sections (50 km)
.
4. Guna-Etawah via Shivpur-Gwalior-Bhind (348 km) 608 569 20 (1) Guna-Bhind (308 km): Completed.
(2) Bhind-Etawah (36 km): track linking completed. Finishing works taken up.
.
5. Lalitpur-Satna, Rewa-Singrauli and Mahoba-Khajuraho NL (541 km) 1631 514 79 (1) Mahoba-Khajuraho (65 km) & Lalitpur-Chhatarpur (134 km) completed. Work has been taken up in remaining portion.
.
6. Ratlam-Dungarpur via Banswara (176 km) 2083 26 25 Land acquired and earthwork in formation and bridge works have been taken up in two stretches (km 0-17 & km 106-123). In balance portion, land acquisition has been taken up.
.
GAUGE CONVERSION
7. Chhindwara-Mandla Fort (182 km) 738 39 20 Earthwork, bridges and ballast supply works have been taken up.
.
8. Chhindwara-Nagpur (149 km) 586 478 100 Earthwork, bridges and tunnel works have been taken up.
.
9. Gwalior-Sheopurkalan with extension to Kota (284 km) 3712 3.5 10 Land acquisition has been taken up.
.
10. Jabalpur-Gondia including Balaghat-Katangi (285 km) and Katangi-Tirodi 1038 714 100 Balaghat-Katangi (46.80 km) & Gondia-Balaghat including MOIL Limited siding (42.7 km): completed.
Balaghat-Nainpur (75 km): Earthwork and bridge works taken up. Work held up for want of forestry clearance.
Nainpur-Jabalpur (113 km): Earthwork, bridge/ROB/RUB work taken up.
Katangi-Tirodi (15 km) New Line: Land acquisition taken up.
.
11. Ratlam-Mhow-Khandwa-Akola (473 km) 1421 315 90 Ratlam-Fatehabad (80 km): completed.
Fatehabad-Indore (40 km): at advance stages of completion. Detailed estimate Akola-Akot (43.5 km) sanctioned. Earthwork and bridge works have been taken up.
.
DOUBLING
12. Barkhera-Habibganj 3rd line (41 km) 202 1 8 Detailed estimate preparation taken up.
13. Bhopal-Beena 3rd line (143 km) 853 738.5 48 Nishatpura-Bina (136 km): completed. Work at advance stage in remaining portion.
.
14. Bina-Kota (283 km) 1125 77 42 Earthwork and bridge works have been taken up.
.
15. Budhni-Barkhera 3rd line (33 km) 287 22 1 Preparation of Detailed Estimate has been taken up.
.
16. Ghat Pindrai-Belkherea Patch (5.5 km) 29 2 10 Earthwork, bridge and ballast supply works have been taken up.
.
17. Guna-Ruthiyai (20 km) 143 20 20 Earthwork & bridges works have been taken up.
.
18. Itarsi-Budhni 3rd line (25 km) 152.5 1 8 Preparation of Detailed Estimate has been taken up.
*****
Source:rajyasabha.nic.in

Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy