CRS Inspection fro doubling of work between Bhagwangola and Jiaganj on 16/10/14
Traffic and Power Block between Jiaganj-Lalgola from 20/21 - 28/29 November for doubling work and OHE work before Pre NI/NI
Bhagirathi Express Bhagirathi Express Sealdah - Lalgola Passenger Lalgola - Sealdah Passenger Lalgola - Sealdah MEMU Sealdah - Lalgola Fast Passenger Lalgola - Ranaghat EMU Passenger Lalgola - Sealdah Passenger Sealdah - Lalgola MEMU Lalgola - Sealdah MEMU Sealdah - Lalgola MEMU Lalgola - Kolkata MEMU Jiaganj Lalgola Bhagwangola
Traffic Block for Pre NI and NI Work
on 27/28 November between Jiaganj and Bhagwangola (23.20 hrs-03.20 hrs)
on 29/30 November between Jiaganj and Lalgola ( 23.10 hrs -00.40 hrs)
on 30 November at Jiaganj Station ( 00.40 hrs -04.40 hrs) (Power Block also)
on...
more...
on 27/28 November between Jiaganj and Bhagwangola (23.20 hrs-03.20 hrs)
on 29/30 November between Jiaganj and Lalgola ( 23.10 hrs -00.40 hrs)
on 30 November at Jiaganj Station ( 00.40 hrs -04.40 hrs) (Power Block also)
on...
more...