Search Forum
Blog Entry# 1350651
Posted: Jan 24 2015 (22:05)
8 Responses
Last Response: Jan 28 2015 (15:12)
8 Responses
Last Response: Jan 28 2015 (15:12)
Shornur Calicut electrified double line will commission on NEXT MONTH.
But NO progress for substations
But NO progress for substations
3 Posts
As per the news in Hindu - If every things go as planned, electric trains will run on the Kozhikode-Shoranur stretch by the end of March 2015. In the first phase, only MEMU trains will be operated between Kozhikode and Shoranur, while passenger express and super-fast trains will be electrified only after the completion of electrification of the Shoranur-Mangalapuram stretch. (Don't know which MEMU???)
I doubt the statement "CLT don't have the facility to for the loco change". Why three line is required for loco change?
I doubt the statement "CLT don't have the facility to for the loco change". Why three line is required for loco change?
New article in todays Malayala Manorama regarding electrification