Is Daund Manmad route electrification work complete, since it started way back in 2011
1 Posts
Daund station will be electrified by Aug 2015 according to a TOI report, Is everything else is complete on Daund Manmad route excluding Daund stationn.
All work has been done...
Only DDAP,DDJA,DDAM & DD
These section's work is remaing which is under progress.....
Actully here, too much no. Of tracks.
That is the reason, takes time..
Only DDAP,DDJA,DDAM & DD
These section's work is remaing which is under progress.....
Actully here, too much no. Of tracks.
That is the reason, takes time..
#Daund_Manmad_Section :-
01) 93% of work completed.
02) Work in balance Puntamba-Daund section is in progress.
03) Target date for completion of work is 31.03.2015.
04) Doubling of this work is not a...
more...
01) 93% of work completed.
02) Work in balance Puntamba-Daund section is in progress.
03) Target date for completion of work is 31.03.2015.
04) Doubling of this work is not a...
more...