What's the latest update on Gorakhpur-Chhapra route and the Chhapra-Varanasi route electrification
Chappra Gorakhpur 90 percent completed.ohe erection and wiring done till gkc.almost all traction substation ready.gkp-cpr will energize in may 2015(max).gkp-gd will take another 2 month from may 2015.whereas cpr-bsb will take at least 3- 4 years.
Why 3-4 years for bsb-cpr electrification , is it not sanctioned yet