Feb 16 2015 (12:30) GR/Kalaburagi Junction (Gulbarga) (4 PFs)
SunilKulkarni~
SunilKulkarni~ 2006 blog postsBidar Gulbarga Line updates
--Almost tracks from Gulbarga station till Kamalapur is layed with some gaps in between for ROB/RUB and minor bridges...
--- Bennethora Bridge near Kurikota is completed only tracks needs to be layed
--- By this month end Engine will roll from Gulbarga station till kilometer 21 which will pass Bennethora bridge also and reach mahagoan
---...
more...
--Almost tracks from Gulbarga station till Kamalapur is layed with some gaps in between for ROB/RUB and minor bridges...
--- Bennethora Bridge near Kurikota is completed only tracks needs to be layed
--- By this month end Engine will roll from Gulbarga station till kilometer 21 which will pass Bennethora bridge also and reach mahagoan
---...
more...
2 Public Posts - Mon Feb 16, 2015
For gulbarga pit line the work is happening at slow very slow pace... not at all impressed by CR work :-( may be it will take another 2 months ( and I am hearing the same 2 months story from past 6 months by CR officials)
4 Public Posts - Mon Feb 16, 2015
1 Public Posts - Tue Feb 17, 2015